moladi
construction process
moladi
formwork system
Affordable Housing Example
moladi
construction process
Position raft foundation
former
Dig Foundation trenches
Place underlay and
reinforcing according to Engineer design and cast dense concrete
Power float slab
Erect
moladi plastic shutter formwork
Place plumbing and
electrical pipes-window and door frames - reinforcing - roof truss blockouts
- 4 hours.
Fill
moladi formwork with mortar (concrete without stone), either
by bucket or pump - 2 hours
Remove the
moladi formwork the
following day.
Fix Ceiling, roof,
electrical wiring, paint glaze, etc.
Complete
moladi
Advantages:
Reduce transport
cost
Reduce building
construction time
Reduce skill
dependence
Superior
structural strength
Employ local
labour
Increased
productivity
Use local
materials